UPDATE ON GROSSE ILE SWING BRIDGE

PHASE 1- STARTING CONSTRUCTION DATE: SPRING/SUMMER 2019

Work will take place below the water surface. Once this is complete, concrete coring and geotechnical boring from top of footing into the bedrock will be performed.

 

TIMELINE FOR PHASE 1:

CONSTRUCTION WORK PERFORMED BY WAYNE COUNTY APPROVED CONTRACTOR

  • Wayne County Process: Fall/Winter 2018
  • Anticipated Construction Dates: Spring/Summer 2019
  • Anticipated Coring/Boring Dates: Summer 2019

 

PHASE 2- STARTING CONSTRUCTION DATE:  SPRING/SUMMER 2020

Work includes: abutment and pier concrete repairs, structural steel repairs, repainting structural steel, mechanical repairs, and electrical repairs.

 

TIMELINE FOR PHASE 2:

CONSTRUCTION WORK PERFORMED BY WAYNE COUNTY APPROVED CONTRACTOR

  • Wayne County Process: Fall/Winter 2019
  • Construction Start: Spring/Summer/Fall 2020

 

Information signs will be posted to alert motorists of bridge work. The construction work above is anticipated. Unforeseen events could cause a slight delay to this schedule.

Wayne County is committed to the safety of its roads and bridges.  The County has 232 bridges within its 43 communities. For updates and questions, the public can contact the Wayne County Roads Division at 888.ROAD CREW.